Labour Cost Intelligence

Workforce activity converted into financial impact.

Monthly Labour Cost
RM 105,144
Rolling 30-day window, regular + OT
Overtime Cost
RM 4,660
4% of monthly total
Idle Labour Cost Estimate
RM 30,006
Paid but underutilised — Attention band workers
Budget Utilization
60%
Est. actual cost vs total WP budget

Labour Cost Trend

Total Cost by Worker Type

6-month cumulative labour cost (regular + overtime) per worker type.

Work Package Budget Reconciliation

Estimated actual cost is derived by matching each work package's trade categories to workers' recorded hours × rate. This is an approximation — a direct worker↔work-package assignment table does not yet exist in the schema. Figures for completed packages use their audited actual cost.

Over budget: 1Under: 10
Package CodeCategoryBudgetEst. Actual CostVarianceStatus
WP-BKT2SA-015In ReviewFinishingRM 95,000RM 108,416RM -13416.00Over Budget
KSK/BKT2SA/005CompletedEarthworksRM 220,000RM 219,200+RM 800.00On Budget
WP-BKT2SA-002On GoingSafety Health & EnvironmentRM 42,000RM 32,167+RM 9,833Under Budget
KSK/BKT2SA/013CompletedStructuralRM 180,000RM 162,000+RM 18,000On Budget
KSK/BKT2SA/010CompletedSafety Health & EnvironmentRM 22,000RM 400.00+RM 21,600Under Budget
KSK/BKT2SA/001CompletedProtectionRM 85,000RM 62,000+RM 23,000Under Budget
KSK/BKT2SA/014CompletedEarthworksRM 55,000RM 24,000+RM 31,000Under Budget
WP-BKT2SA-008On GoingStructuralRM 140,000RM 86,192+RM 53,808Under Budget
WP-BKT2SA-009In ReviewPlumbingRM 88,000RM 24,645+RM 63,355Under Budget
WP-BKT2SA-004In ReviewFinishingRM 95,000RM 28,375+RM 66,625Under Budget
WP-BKT2SA-006On GoingM&ERM 175,000RM 88,583+RM 86,417Under Budget
WP-BKT2SA-011On GoingFinishingRM 115,000RM 3,680+RM 111,320Under Budget
WP-BKT2SA-003On GoingStructuralRM 310,000RM 134,066+RM 175,934Under Budget
Total budget: RM 1,622,000Total est. cost: RM 973,72413 packages

Idle Cost Breakdown — Attention Required Workers

Workers in the Attention band (<70 utilisation score) driving the idle cost estimate. Each figure represents wages paid for unproductive hours in the last 30 days. Review the Productivity Analytics page for full scoring detail.

Worker NameTypeScoreEst. Idle Cost (30d)
Kevin Tan Yong ShengStaff52 ptsRM 2,432
Nurul Ain binti MalikStaff37 ptsRM 2,235
Kumaresan a/l SamySubcon47 ptsRM 1,297
Loh Chin KeongSubcon40 ptsRM 1,237
Lee Chee WahSubcon55 ptsRM 1,233
Ravi a/l GunasegaranSubcon50 ptsRM 1,229
Ariffin bin Md SallehSubcon63 ptsRM 1,206
Vijay a/l DevarajanSubcon51 ptsRM 1,197
Raziman bin OsmanSubcon50 ptsRM 1,193
Shamsul bin BakarSubcon51 ptsRM 1,176
Mohd Hafiz bin IsmailSubcon48 ptsRM 1,169
Firdaus bin RosliSubcon50 ptsRM 1,155
Chia Kok WengSubcon66 ptsRM 1,140
Azwan bin MansorSubcon61 ptsRM 1,097
Tan Beng HuatSubcon63 ptsRM 1,042
Lim Yew HengSubcon As GW46 ptsRM 825.00
Heng Kim SweeSubcon As GW37 ptsRM 773.00
Effendi bin YusoffSubcon As GW37 ptsRM 727.00
Hairul bin AzmiGeneral Worker47 ptsRM 722.00
Selvam a/l PonnusamyGeneral Worker52 ptsRM 681.00
Ahmad Razif bin KamalGeneral Worker62 ptsRM 667.00
Norazam bin TalibSubcon As GW29 ptsRM 662.00
Azri bin LatifGeneral Worker56 ptsRM 656.00
Ganesh a/l RamanGeneral Worker50 ptsRM 651.00
Lim Ah KowGeneral Worker62 ptsRM 633.00
Periasamy a/l DuraiSubcon As GW25 ptsRM 633.00
Karunakaran a/l NairSubcon As GW24 ptsRM 631.00
Chong Wei MingGeneral Worker60 ptsRM 621.00
Mohd Faizal bin OthmanGeneral Worker67 ptsRM 556.00
Noor Azam bin RashidGeneral Worker68 ptsRM 530.00
Total idle cost estimateRM 30,006