Work Package Listing
BKT2SABudget and physical-progress tracking — Labour, Preliminary, and sub-types
Work packages currently in progress with active field operations
WP-BKT2SA-002
Created by Kevin Tan Yong Sheng • 22 Oct 2024
LabourSafety Health & Environment
Work Nature:Work On Behalf
Remark: Safety officer deployment and daily toolbox briefings
Budget Amount:RM 42,000
Physical Progress
87%Complete
WP-BKT2SA-003
Created by Kevin Tan Yong Sheng • 01 Nov 2024
LabourStructural
Block B, Basement Level
Work Nature:Reinforced Concrete Works
Remark: Basement slab pours — Levels B1 and B2
Budget Amount:RM 310,000
Physical Progress
62%Complete
WP-BKT2SA-006
Created by Kevin Tan Yong Sheng • 15 Nov 2024
LabourM&EElectrical
Block A, Electrical Riser
Work Nature:Main Electrical Distribution
Budget Amount:RM 175,000
Physical Progress
45%Complete
WP-BKT2SA-008
Created by Nurul Ain binti Malik • 20 Nov 2024
LabourStructural
Work Nature:Formwork Installation
Budget Amount:RM 140,000
Physical Progress
71%Complete
WP-BKT2SA-011
Created by Kevin Tan Yong Sheng • 10 Jan 2025
LabourFinishing
Block B, Level 2
Work Nature:Tiling Works
Remark: Wet areas and common corridors — early mobilisation
Budget Amount:RM 115,000
Physical Progress
5%Complete