Work Package Listing

BKT2SABudget and physical-progress tracking — Labour, Preliminary, and sub-types

Work packages currently in progress with active field operations

WP-BKT2SA-002

Created by Kevin Tan Yong Sheng • 22 Oct 2024

Nurul Ain binti Malik
LabourSafety Health & Environment
Work Nature:Work On Behalf
Remark: Safety officer deployment and daily toolbox briefings
Budget Amount:RM 42,000

Physical Progress

87%Complete

WP-BKT2SA-003

Created by Kevin Tan Yong Sheng • 01 Nov 2024

Shahril bin Ramli
LabourStructural
Block B, Basement Level
Work Nature:Reinforced Concrete Works
Remark: Basement slab pours — Levels B1 and B2
Budget Amount:RM 310,000

Physical Progress

62%Complete

WP-BKT2SA-006

Created by Kevin Tan Yong Sheng • 15 Nov 2024

Nurul Ain binti Malik
LabourM&EElectrical
Block A, Electrical Riser
Work Nature:Main Electrical Distribution
Budget Amount:RM 175,000

Physical Progress

45%Complete

WP-BKT2SA-008

Created by Nurul Ain binti Malik • 20 Nov 2024

Shahril bin Ramli
LabourStructural
Work Nature:Formwork Installation
Budget Amount:RM 140,000

Physical Progress

71%Complete

WP-BKT2SA-011

Created by Kevin Tan Yong Sheng • 10 Jan 2025

Nurul Ain binti Malik
LabourFinishing
Block B, Level 2
Work Nature:Tiling Works
Remark: Wet areas and common corridors — early mobilisation
Budget Amount:RM 115,000

Physical Progress

5%Complete